Phase 1: Assessment
Typical duration: 4–8 weeks
Key Deliverables
Current-state documentation: power, cooling, network, compute, storage
Gap analysis: current capability vs. required capability
Risk assessment: reliability, performance, compliance, strategic
Preliminary scope definition and budget range
Phase Gate Criteria
Current-state documentation complete. Gap analysis reviewed and approved by stakeholders. Budget range approved by executive sponsor.
Phase 2: Design
Typical duration: 6–12 weeks
Key Deliverables
Detailed design documents: power, cooling, network, compute, storage
Compliance requirements incorporated into design
Bill of materials for procurement
Construction drawings and specifications
Commissioning plan and acceptance criteria
Phase Gate Criteria
Design documents reviewed and approved by technical stakeholders. Compliance requirements verified by legal/compliance team. Bill of materials approved for procurement.
Phase 3: Procurement
Typical duration: 8–16 weeks
Key Deliverables
Hardware purchase orders placed with OEM-authorized vendors
Lead time tracking for all long-lead items
Delivery schedule aligned with construction sequence
Staging and receiving plan
Phase Gate Criteria
All purchase orders placed. Lead times confirmed. Long-lead items (UPS, generators, switchgear) delivery dates confirmed and aligned with construction schedule.
Phase 4: Construction
Typical duration: 12–24 weeks
Key Deliverables
Power infrastructure installed and energized
Cooling infrastructure installed and operational
Network infrastructure installed and cabled
Compute and storage hardware racked and stacked
Physical security controls installed
Phase Gate Criteria
All infrastructure installed per design specifications. Pre-commissioning checks complete. No open safety issues. Commissioning team on-site and ready.
Phase 5: Commissioning
Typical duration: 4–8 weeks
Key Deliverables
Power system testing under load (UPS, generator, transfer switches)
Cooling system testing at target power densities
Network performance testing (throughput, latency, failover)
Compute and storage performance validation
Commissioning report with all test results
Phase Gate Criteria
All commissioning tests passed. No open critical or high findings. Commissioning report reviewed and accepted. Migration team briefed on infrastructure state.
Phase 6: Migration
Typical duration: 4–16 weeks
Key Deliverables
Workload migration executed per migration sequence
Each workload validated in new environment before legacy decommission
Rollback executed for any failed migration events
Legacy infrastructure decommissioned after all workloads validated
Phase Gate Criteria
All workloads migrated and validated. No open production issues. Legacy infrastructure decommissioned. Operations team confirmed ready for steady-state operations.
Phase 7: Closeout
Typical duration: 2–4 weeks
Key Deliverables
As-built drawings updated to reflect actual installation
Operating procedures documented and delivered
Maintenance schedules established
Warranty documentation compiled
Lessons learned documented
Phase Gate Criteria
All deliverables accepted by client. Final payment released. Warranty period commenced. Operations team confirmed in steady-state.
Timeline ranges reflect program complexity