Timeline note
Phase 01: Assessment and Requirements
Typical duration: 4–8 weeks
Milestones
- →Workload assessment complete
- →Site readiness assessment complete
- →Compliance requirements documented
- →Operational model defined
Go/No-Go Criteria
Site can support the planned deployment (or upgrade scope is defined and budgeted). Compliance requirements are documented and reviewed by legal. Executive sponsorship confirmed.
Deliverables
- →Workload requirements document
- →Site readiness report
- →Compliance requirements matrix
- →Project charter
Phase 02: Design and Procurement
Typical duration: 8–16 weeks
Milestones
- →System architecture document approved
- →Bill of materials finalized
- →GPU hardware ordered
- →Long-lead items ordered
Go/No-Go Criteria
System architecture reviewed and approved by IT, facilities, security, and compliance. Budget approved. Procurement initiated for long-lead items.
Deliverables
- →System architecture document
- →Bill of materials
- →Purchase orders for hardware
- →Procurement schedule
Phase 03: Site Preparation
Typical duration: 8–20 weeks
Milestones
- →Power infrastructure upgrades complete
- →Cooling infrastructure installed
- →Network cabling complete
- →Staging area prepared
Go/No-Go Criteria
Power infrastructure tested and certified. Cooling system commissioned and tested. Network cabling tested. Site ready for hardware installation.
Deliverables
- →Power infrastructure commissioning report
- →Cooling system commissioning report
- →Network cabling test results
- →Site readiness sign-off
Phase 04: Hardware Installation
Typical duration: 2–6 weeks
Milestones
- →GPU servers racked and cabled
- →Network switches installed and configured
- →Storage systems installed
- →Power and cooling connected
Go/No-Go Criteria
All hardware installed and powered on. Network connectivity verified. Storage accessible from all compute nodes. Power and cooling within design parameters.
Deliverables
- →Hardware installation report
- →Network configuration documentation
- →Storage configuration documentation
Phase 05: Software Configuration
Typical duration: 2–4 weeks
Milestones
- →Operating system deployed on all nodes
- →GPU drivers and CUDA installed
- →Network fabric configured (InfiniBand or RoCEv2)
- →Storage file system configured
- →Cluster management software deployed
Go/No-Go Criteria
All nodes accessible via management network. GPU drivers installed and GPUs recognized. Network fabric operational. Storage file system mounted on all compute nodes.
Deliverables
- →Software configuration documentation
- →Cluster management runbook
- →Storage configuration runbook
Phase 06: Commissioning and Testing
Typical duration: 2–4 weeks
Milestones
- →GPU benchmark tests passed
- →Network throughput tests passed
- →Storage throughput tests passed
- →Full-cluster training job completed
- →Acceptance criteria met
Go/No-Go Criteria
All acceptance criteria met. Full-cluster training job completed successfully. Power and cooling within design parameters under full load. Client sign-off obtained.
Deliverables
- →Commissioning test report
- →Acceptance test results
- →As-built documentation
- →Operations runbook
Phase 07: Operations Handover
Typical duration: 2–4 weeks
Milestones
- →Operations team trained
- →Runbooks reviewed and approved
- →Monitoring and alerting configured
- →Support contracts activated
- →First production workload running
Go/No-Go Criteria
Operations team trained and certified. Monitoring and alerting operational. Support contracts active. First production workload running successfully.
Deliverables
- →Operations training completion certificates
- →Monitoring configuration documentation
- →Support contract activation confirmation